Inside a Kafka migration assessment: the twelve areas we review

Before moving to Confluent Cloud or Confluent Platform, we review twelve areas, from business requirements and infrastructure to security, data integration, applications, compliance and cost. What each covers and why.

Most Kafka migrations that go wrong were in trouble before the first topic was replicated. The new cluster was sized from the old one's broker count rather than its traffic. An application nobody remembered, consuming from a topic everyone thought was dead, broke at switchover. The new platform's security model didn't map onto the old ACLs, and the gap was found in production.

That's why our migrations start with an assessment. Depending on the size of the estate it takes one to six weeks, and uses automation to discover what is actually running rather than relying on what the wiki says. This article walks through the twelve areas it covers.

1. Business requirements

Who depends on streaming, and how much? We work with stakeholders to capture business units and multi-tenancy, SLAs and criticality per use case, and the current streaming architecture. This decides the order of everything else: the payments feed and the marketing clickstream do not migrate the same way.

2. Infrastructure

Automated discovery of the current clusters and components: versions, deployment model (on premises, cloud, Kubernetes), networking, capacity and traffic, and production and DR topology. The target is sized from measured throughput, partition counts and retention, not from the number of brokers.

3. Governance

How are topics and schemas created today, who approves them, and where are they catalogued? We capture the onboarding process, catalog integration (for example Collibra or Alation), schema management, lineage and audit logs, and design the target equivalents.

4. Operations

Monitoring (Prometheus and Grafana, Datadog, New Relic, AppDynamics), logging (ELK, Splunk), security operations and SIEM feeds, CI/CD and GitOps practice, and any AIOps tooling. Operations is often the area where a managed service changes the most, and where teams need the clearest new runbooks.

5. Security

Encryption in transit and at rest, authentication (SASL mechanisms, OAuth, mutual TLS, custom), authorization (ACLs or RBAC), and secrets management. The key output is a mapping from today's principals and permissions to the target's; see our security guide for the pieces.

6. Data architecture

Topics, schemas, partitions, replication factors, formats and topic management. This is where we find the topics with one partition carrying most of the traffic, the topics with hundreds of partitions carrying almost none, and the retention settings nobody chose.

7. Data integration

Everything that moves data in and out of Kafka: CDC tools, Kafka Connect and its connectors, NiFi, StreamSets and vendor integration tools. Each needs a plan: a managed connector, a self-managed one, or a change of tool.

8. Applications and stream processing

Producers and consumers, Kafka Streams, ksqlDB, Flink and Flink SQL, and Spark applications. For each we record the client library and version, configuration, consumer groups and offsets, and what changes the target requires: bootstrap servers and credentials at least, library upgrades often.

9. Compliance

PCI DSS, HIPAA and GDPR requirements that apply to the data in the topics, and any gaps in the current implementation. Requirements depend on your data and jurisdictions, so we work with your compliance team rather than assume.

10. FinOps

Resource utilisation today and the cost of the target, using our automated cost calculator. Managed services price on different units (throughput, partitions, storage, networking), and the cheapest-looking option is not always the cheapest at your traffic.

11. Tools and runbooks

Runbooks for deployments, upgrades, failover and failback, issue resolution and performance benchmarking, and tools such as Cruise Control. Which still apply, which change, and which disappear on the target.

12. Executive close-out

The findings, the final architecture and the implementation plan, presented to the people who fund and approve the migration. The plan groups topics and applications into waves, lowest risk first.

From plan to project. The migration plan is generated as a project template you can import into Jira, Asana or Trello, with tasks, labels, blocker types and dashboards, so the plan and the work tracker start out identical.

What decides whether it takes one week or six

An assessment typically takes one to six weeks. Where an assessment lands depends less on data volume than on how many things have to be understood:

  • Number of clusters and environments. Each production, DR and non-production cluster is discovered and compared.
  • Number of applications and owners. Every consumer group needs an owner who can say what it does and how critical it is.
  • Integration variety. Ten copies of one connector are quicker to plan than ten different integration tools.
  • Security model distance. Moving from Kerberos and ACLs to OAuth and RBAC takes more mapping than moving between two SCRAM setups.
  • Compliance scope. Topics carrying card or health data need their requirements confirmed before the target is designed.

What we ask you to prepare

  1. A list of the clusters in scope, and who can grant access to each.
  2. Contacts for the main application teams, and for security, compliance and operations.
  3. Any existing architecture documents, runbooks and incident reviews, however out of date.
  4. The constraints you already know: deadlines, contract end dates, change freezes, regions the data must stay in.

Discovery then tells us what is really there, and the interviews tell us what it is for. Neither replaces the other: automation finds the consumer group nobody mentioned, and only a person can tell you whether it can be switched off.

Example · Merrow Mutual, a made-up insurer

Two clusters, one surprise

Merrow runs two self-managed Kafka clusters and wants to move to Confluent Cloud. Its wiki lists 60 topics. Discovery finds more, including a set of topics written by a reporting job that the data team retired a year ago but never switched off. Those topics are excluded from the plan, which shrinks the first wave, and the security mapping shows that three applications still share one service account, which the plan splits before migration rather than carrying across.

All names and details are fictional.

What the assessment is not

It isn't a sales exercise for a particular platform; sometimes the right answer is to stay where you are and fix the operations. And it isn't a document that sits on a shelf: its outputs are the inputs to the migration itself, from the cluster design and configuration mappings to the security mapping and the switchover order. How that switchover works is the subject of cutting over without a big bang.

Questions we are often asked

Can we skip the assessment and start migrating?

For a small estate with a well-documented cluster, a short assessment may be enough. Skipping it entirely means sizing, security mapping and wave planning happen during the migration, where surprises are more expensive.

Does the assessment change anything on our clusters?

It is a review: the purpose is to understand the current setup and design the target. What access discovery uses is agreed with your security team before it starts.

What do we get at the end?

The outputs shown in the diagram: a target architecture, an infrastructure plan, governance and security design, an operations guide and a migration plan in waves, presented at the executive close-out.